NO. 55

A Resolution accepting the lowest responsive, responsible bid for the Clearing for the SW Quadrant of Hill Brady and Skyline project from Midwest Tree Service, LLC, in an estimated amount of $241,437.50, with unit prices prevailing.

BATTLE CREEK, MICHIGAN - 2/7/2017

Resolved by the Commission of the City of Battle Creek:

 

The lowest responsive, responsible bid for the Clearing for the SW Quadrant of Hill Brady and Skyline project is accepted from Midwest Tree Service, LLC, in an estimated amount of $241,437.50, with unit prices prevailing. The City Manager is authorized to execute Contract No. 2017-048B, which will be paid from BU/Accounts: 

440.61.8890.801.310 with Project #BCTIFA-1100 SW Quad Hill Brady/Skyline









I, Victoria Houser, City Clerk of the City of Battle Creek, hereby certify the above and foregoing is a true and correct copy of a Resolution adopted by the Battle Creek City Commission at a Regular meeting held on February 7, 2017.


Victoria Houser


Battle Creek City Commission
2/7/2017
Action Summary

Staff Member: Christine Huff 
Department:Purchasing 
SUMMARY 
A Resolution accepting the lowest responsive, responsible bid for the Clearing for the SW Quadrant of Hill Brady and Skyline project from Midwest Tree Service, LLC, in an estimated amount of $241,437.50, with unit prices prevailing.
BUDGETARY CONSIDERATIONS

HISTORY, BACKGROUND and  DISCUSSION
The solicitation was issued January 11, 2017, for the above-mentioned project. This project consists of removal of all trees and brush, including stumps from a 75-acre site southwest of Hill Brady and Skyline located in Battle Creek, MI. All wood material will be considered the property the successful Bidder.  Site to be raked clean when completed.  

As with all of our construction projects that exceed $50,000, this is a prevailing wage job. Prevailing Wage is defined as the hourly wage, along with benefits and overtime, paid in the largest city in each county, to the majority of workers, laborers, and mechanics. Prevailing wages are established, by the Department of Labor & Industries, for each trade and occupation employed in the performance of public work.

Copies of the IFB were provided to eight contractors and four construction plan houses. Construction companies and the trades subscribe to planhouses to be aware of all jobs being bid around the region.    In addition, an advertisement was placed in the Battle Creek Enquirer and on the City’s website.  Bid responses were due on January 30, 2017.  A bid tabulation is attached.

The bids were reviewed by Kurt Tribbett in Engineering.   A recommendation was made to accept the lowest, responsive, responsible bid as noted above.  I concur with the department’s recommendation that contract award to this firm would be in the best interest of the City of Battle Creek.
DISCUSSION OF THE ISSUE

POSITIONS

ATTACHMENTS:
File NameDescription
Tribbett_memo.docxDepartment support memo
Copy_of_2017-048B_TAB_SW_Quad_Hill_Brady_and_Skyline_Dr.xlsxBid Tab