Item Coversheet

Resolution

NO. 185

A Resolution directing the City Manager to prepare, or cause to be prepared, plans and specifications, an estimate of the cost thereof, and his/her recommendations as to what proportion of such costs should be paid by special assessment and what part, if any, should be a general obligation of the City and the land that should be specifically assessed for the 2019 Dickman Road Business Improvement District Project.

BATTLE CREEK, MICHIGAN - 7/3/2018

Resolved by the Commission of the City of Battle Creek:

 

That, pursuant to Section 216.05 of the Codified Ordinances of Battle Creek, the City Manager is directed to do the following:
1. Prepare plans and specifications for the 2019 Dickman Road Business Improvement District project from M-66 westerly to the city limits.
2. Estimate the cost of the project
3. Recommend how much should be paid by the special assessment and how much, if any, should be a general obligation of the City.
4. Identify the parcels to be specially assessed.









I, Victoria Houser, City Clerk of the City of Battle Creek, hereby certify the above and foregoing is a true and correct copy of a Resolution adopted by the Battle Creek City Commission at a Regular meeting held on July 3, 2018.


Victoria Houser


Battle Creek City Commission
7/3/2018
Action Summary

Staff Member: Steven M. Hudson 
Department:Assessing 
SUMMARY 

A Resolution directing the City Manager to prepare, or cause to be prepared, plans and specifications, an estimate of the cost thereof, and his/her recommendations as to what proportion of such costs should be paid by special assessment and what part, if any, should be a general obligation of the City and the land that should be specifically assessed for the 2019 Dickman Road Business Improvement District Project.


BUDGETARY CONSIDERATIONS

HISTORY, BACKGROUND and  DISCUSSION

This is the first of four resolutions of the special assessment process.  This resolution directs the City Manager to prepare plans, specifications and cost estimates for the 2019 Dickman Road Business Improvement District project.

The Business Improvement District (BID) was created in 2000 in an effort to protect the investments of seven automobile dealers concentrated within a 1 ½ mile stretch by reversing the declining physical environment along West Dickman Road and increasing awareness through collaborative marketing efforts.  The close proximity of the seven dealerships was an under exploited asset to market as the preferred option for consumer shopping. The creation of the BID has allowed marketing efforts to promote and enhance this asset.

The BID was renewed in 2005, 2008, and in 2011 for a three year period each to continue the goal of preserving the asset.  In 2014 the BID was renewed for a five year period.  This resolution renews the BID special assessment for another five year period.

At their May 2018 meeting the Dickman Road Business Improvement District Board of Directors approved the attached five-year special assessment budget plan.


DISCUSSION OF THE ISSUE

POSITIONS

ATTACHMENTS:
File NameDescription
BID_renewal_request_letter_BC_6-13-18.pdfBID Renewal Request Letter 6-13-18
Business_Plan_Executive_Summary_2019.pdfBusiness Plan Executive Summary 2019
Five_year_budget_20-24.pdfFive Year Budget 2020-2024